TUNNELLING & UNDERGROUND SPACE TECHNOLOGY · 2026
H型钢替代灌注桩TRD复合墙体刚度提升新突破
H-Section Steel Replaces Bored Piles:A Breakthrough in TRD Composite Wall Stiffness
ScienceDirect 学术前沿 · Soft Soil Deep Excavation Optimization
等厚度水泥土连续墙(TRD工法)以其卓越的止水性和连续成墙品质,近年来在软土地区深基坑工程中快速普及。然而,水泥土抗拉强度低的先天局限,使其通常需要内插混凝土灌注桩才能承担主动土压力——这一做法工序繁琐、成本高昂。2026年一季度,国际顶刊 Tunnelling and Underground Space Technology发表最新研究,提出以H型钢替代混凝土灌注桩,在保持甚至提升围护刚度的同时,大幅降低施工复杂度。
The TRD (Trench Cutting Re-mixing Deep wall) method has rapidly gained adoption in soft-soil deep excavation projects due to its superior water-tightness and seamless wall quality. However, its inherently low tensile strength requires the insertion of concrete bored piles to resist lateral earth pressure — a practice that is costly and complex. In Q1 2026, the leading international journal Tunnelling and Underground Space Technologypublished research proposing to replace concrete bored piles with H-section steel beams, maintaining or enhancing retaining stiffness while significantly reducing construction complexity.
▍01 / 研究背景:TRD工法的潜力与瓶颈
Research Background: The Promise and Limitations of TRD Method
TRD工法(Trench Cutting Re-mixing Deep wall method)由日本神户制钢所于1993年研发,通过链锯式切割箱横向推进,在地下形成无接缝、等厚度的水泥土连续墙。其最大深度可达80m,适用于砂土、黏土、卵砾石等各类复杂地层,止水效果显著优于传统三轴搅拌桩。
Developed by Kobe Steel, Japan in 1993, the TRD method uses a chain-saw cutting box advancing horizontally to form a seamless, uniform-thicknesssoil-cement wall underground. It reaches depths up to 60 m and is applicable to sand, clay, gravel and other complex strata, offering far superior water-tightness compared to conventional triple-axis mixing piles.

然而,水泥土墙体抗拉强度仅为抗压强度的1/10左右,无法独立承受基坑开挖产生的弯矩。传统解决方案是在TRD墙内插入混凝土灌注桩(钻孔桩),形成类SMW工法复合支护体系——但这带来了三大痛点:
However, the tensile strength of soil-cement is only ~1/10 of its compressive strength, making it unable to independently resist the bending moment caused by excavation. The conventional solution is to insert concrete bored piles into the TRD wall — forming a SMW-like composite system — but this creates three major pain points:
-
① 施工工序复杂,灌注桩泥浆污染处理麻烦
Complex construction sequence; slurry disposal from bored piles is troublesome.
-
② 垂直度控制困难,易与TRD墙体发生碰撞偏斜
Verticality control is difficult; the pile can deviate and collide with the TRD wall.
-
③ 工期长,造价高,可重复利用性差
Long construction period, high cost, and the pile cannot be recovered for reuse.
本研究提出的核心方案:将TRD墙内的混凝土灌注桩全部替换为H型钢,使水泥土墙与H型钢形成”整体式墙-桩复合支护体系”(Integrated Wall-Pile Primary Support)。
The core proposal of this study is to replace all concrete bored piles with H-section steel beamsinserted into the TRD wall, forming an “Integrated Wall-Pile Primary Support” system in which the soil-cement wall and H-beams act compositely.
支护体系结构对比 · System Comparison
❌ 传统方案 / Conventional
TRD水泥土墙 + 混凝土灌注桩
TRD wall + concrete bored piles(分体施工 / Separate construction)
✅ 本研究方案 / This Study
TRD水泥土墙 + H型钢(内插)
TRD wall + H-section steel beams(整体复合 / Integrated composite)
“Trench cutting re-mixing deep walls can effectively mitigate water ingress and seepage; however, their low tensile strengths prevent them from serving as independent primary support… The wall stiffness can be effectively enhanced by replacing the concrete bored piles with H-section steel beams; this replacement results in an integrated wall–pile primary support system.”
「等厚水泥土连续墙能有效阻止渗水,但其低抗拉强度使其无法独立作为主支护……将混凝土灌注桩替换为H型钢可有效提升墙体刚度,形成整体式墙-桩复合支护体系。」

| | | |
|---|---|---|
| 施工工序 | | 简单(内插即用) |
| 墙体刚度 | | 有效提升,整体性强 |
| 垂直度控制 | | 容易(水泥土中插入) |
| 环境影响 | | 绿色低污染 |
| 可回收利用 | | ✅ H型钢可拔出复用 |
| 适用场景 | | 软土深大基坑(优选) |
▲ TRD三步施工工艺流程:先行挖掘 → 回撤挖掘 → 搅拌成墙3-cycle method: Pre-cutting → Back-cutting → Final mixing & wall formation
TRD成墙施工
TRD Wall Formation
链锯式切割箱竖向切割至设计深度(最深80m),水平推进同时注入水泥固化液,原位搅拌形成等厚度连续水泥土墙。
The chain-saw cutting box cuts vertically to design depth (up to 60 m) and advances horizontally, injecting cement slurry to form a uniform-thickness continuous soil-cement wall in situ.
H型钢插入
H-Section Steel Insertion
在水泥土初凝前(通常施工完成后4–6小时内),按设计间距将H型钢竖向插入尚具流动性的水泥土墙中,利用起重设备精确定位。
Before initial setting of the soil-cement (typically within 4–6 hours), H-section steel beams are inserted vertically at design spacing into the still-fluid mix, positioned precisely with lifting equipment.
复合体形成与养护
Composite Formation & Curing
水泥土与H型钢共同养护28天,水泥土凝固后与H型钢紧密结合,形成刚度显著高于纯水泥土墙的复合围护结构。
The soil-cement and H-beams are cured together for 28 days. Once hardened, they bond tightly to form a composite retaining structure with significantly higher stiffness than a plain soil-cement wall.
基坑开挖 → H型钢回收
Excavation → H-Steel Recovery
基坑开挖完成后,根据设计要求可将H型钢拔出回收再利用,进一步降低工程综合成本。
After excavation is complete, the H-section beams can be extracted and reused according to design requirements, further reducing overall project costs.

H型钢与TRD复合支护的实践已在国内多个软土城市深基坑项目中得到应用,以下为典型参数参考:
The TRD + H-steel composite system has been applied in multiple soft-soil urban deep excavation projects across China. Representative project parameters are referenced below:
🏢 南昌华茂广场基坑项目
Nanchang Huamao Plaza Deep Excavation
深基坑围护工程 | 复杂地质条件 · Complex geological conditions
SMW复合工法
TRD墙深 / Depth
22–25m
插入地层 / Strata
强风化岩
Weathered rock
型钢配置 / Steel
H型钢
🚇 杭州余杭地铁车站基坑
Hangzhou Yuhang Metro Station Excavation
城市地铁工程 | 软土地层 · Urban metro in soft soil
TRD围护
帷幕深度 / Depth
40–50m
墙厚 / Thickness
700mm
优化目标 / Goal
H型钢替代
H-beam replace
本研究从理论层面为”TRD+H型钢”复合支护体系提供了系统的力学验证依据,具有以下行业价值:
This study provides systematic mechanical validation for the TRD + H-steel composite system at the theoretical level, offering the following industry value:
-
🔬 理论支撑:建立了TRD+H型钢复合体系的变形计算模型,填补了设计规范空白
Theoretical foundation:Establishes a deformation calculation model for the TRD + H-steel system, filling a gap in design codes.
-
💰 经济价值:H型钢可拔出回收利用,降低工程全生命周期成本,相比灌注桩节省可观
Economic value:H-beams are recoverable for reuse, reducing lifecycle costs considerably compared to abandoned bored piles.
-
🌿 绿色施工:减少泥浆废弃物,符合建筑业绿色低碳发展趋势
Green construction:Reduces slurry waste, aligning with the construction industry’s green and low-carbon development trend.
-
🌏 应用前景:对越南、东南亚等软土地区大规模基础设施建设(地铁、机场、高速)具有重要推广价值
Global application:Highly relevant for large-scale infrastructure in soft-soil regions such as Vietnam and Southeast Asia (metro, airport, expressway projects).
📑 基础设施建设技术前沿 · Infrastructure Technology Frontier
本文内容整理自公开学术摘要,
编辑整理:项敏
仅作传播分享知识所用。
如有侵权,请联系编辑撤稿。
